.truncate { white-space: nowrap; text-overflow: ellipsis; }

Skeg Ripped from Azipod

Case Study

Skeg Ripped from Azipod

Technical Situation

Cruise Ship, length 290 meter, 113,323 Tons Gross Tonnage
3 month out of dry dock, galvanic corrosion caused heavy cavitation/erosion damage on PORT and STBD side rudders.
Section loss up to 100% was repaired by build-up welding with underwater wet welding techniques. One of the rudders was filled with water.
Subsea Global Solutions together with cruise line and class developed a repair plan involving the qualification of underwater wet welded groove weld procedures to AWS D3.6 Class A requirements.
Over a time period of three month Subsea Global Solutions crew sailed with the vessel, during port stops divers were deployed to restore the wasted material.
Repair was considered permanent and was performed without interrupting the itinerary of the vessel.
CONTACT US

About the Author:
Tags:

More Articles:

Looking for underwater maintenance and repair services?

Contact Us 24/7
Request Service